RWE has completed the sale of its 33.33% stake in the 1.1 GW Five Estuaries offshore wind farm off the east coast of England to EDF power solutions UK and Ireland, with EDF taking over as lead developer, the German utility announced on 8 October 2026.
Five Estuaries is an extension of the operating Galloper wind farm in the southern North Sea. The project is consented to comprise up to 79 wind turbines with a maximum tip height of 370 metres, plus foundations. It received development consent from the UK Secretary of State for Energy Security and Net Zero on 17 December 2025. The project covers two seabed areas totalling about 128 square kilometres.
Before the sale, ownership was split between RWE, a Macquarie-led consortium, ESB and Sumitomo Corporation. RWE held a 33.33 per cent stake in the 1.1 GW offshore wind project, with the remainder held by a Macquarie-led consortium on 25 per cent, ESB on 20.83 per cent and Sumitomo Corporation on 20.83 per cent. EDF now takes RWE’s position alongside those three partners.

Why RWE is exiting now
RWE framed the move as portfolio management rather than a retreat from UK offshore wind. RWE said it plans to reinvest the sale proceeds in its existing portfolio of consented offshore wind projects and would continue to support Five Estuaries in the short term to facilitate the transition to the new ownership, adding that the project’s priority is to move from development into construction and, ultimately, operation. The company remains a large player in the market: RWE was the biggest winner in last year’s UK Contracts for Difference Allocation Round 7 for offshore wind, winning awards for five offshore projects amounting to a combined installed capacity of 6.9 gigawatts.
EDF, for its part, becomes lead developer on a project that still needs to reach a final investment decision before construction can start. According to information on the Five Estuaries website, the developers are targeting first construction activities in 2028 and for the wind farm to be operational by the end of the decade. Once built, the farm’s power will reach shore through subsea cables. Electricity generated by Five Estuaries would be transmitted ashore via subsea cables to Sandy Point, between Frinton-on-Sea and Holland-on-Sea in Essex, with underground cables connecting to a new substation west of Little Bromley before eventually joining the proposed Norwich–Tilbury transmission corridor.
The sale is one of several ownership changes moving through the UK offshore wind sector this week. Ørsted has separately exercised a buyback right to take full control of the smaller, operating Gunfleet Sands wind farm, while OEG has signed a contract with Ørsted to supply temporary power during construction of the much larger Hornsea 3 project. Developers are actively reshuffling stakes across projects at every stage, from operating assets to projects years from construction, as capital needs and strategies shift.
At a glance
| Item | Detail |
|---|---|
| What | Sale of 33.33% stake, lead developer role transferred |
| Buyer / seller | EDF power solutions UK and Ireland / RWE |
| Project | Five Estuaries offshore wind farm, 1.1 GW, southern North Sea |
| Status | Consented (December 2025); not yet under construction |
| Announced | 8 October 2026 |
What to watch
Attention now turns to when the joint venture partners take a final investment decision and whether the project stays on course for construction activity from 2028.
Sources
- Source: RWE completes sale of shares in Five Estuaries Offshore Wind Farm (RWE press release)
- Source: EDF Buys RWE’s Stake in 1.1 GW UK Offshore Wind Farm (Offshore Wind)
- Source: RWE confirms Five Estuaries stake sale (reNEWS)
- Source: RWE sells 33.33% stake in Five Estuaries offshore wind project to EDF (Renewables Now)
Header image: official press image from rwe.com.