Spanish energy and chemicals group Moeve has started construction of the first phase of its Andalusian Green Hydrogen Valley in Huelva, Spain, a $1.2 billion investment in a 300 MW electrolyser plant that the company says is on track to become Europe’s largest renewable hydrogen project, Engineering News-Record reported on 14 October 2026.
Moeve has launched the $1.2-billion first phase of the Andalusian Green Hydrogen Valley project at a coastal in-country site that is set to be Europe’s largest renewable hydrogen energy project. The first phase, named Onuba, is being built at Moeve’s Energy Park in Palos de la Frontera. Moeve, with a 51% majority stake in the project, will lead first phase development to build a facility with 300 MW electrolysis capacity that will produce about 45,000 tons per year.
What is new
Construction on Onuba broke ground in late September 2026, and the latest reporting confirms the project has now moved from final investment decision into the build phase. The developers say the project will save 250,000 tons annually of carbon dioxide emissions and is expandable to 405 MW, depending on grid availability.
The first phase is only part of a much bigger plan. The estimated $3.3-billion effort aims to develop a total of 2 GW of combined electrolysis capacity to produce up to 300,000 metric tons per year of green hydrogen to be used to decarbonize chemical, steel, cement, heavy maritime transport and aviation sectors. Moeve also says the full valley project will help establish the first major maritime green hydrogen corridor connecting southern and northern Europe via the Port of Rotterdam.
Who else is involved
The ownership structure mixes industrial and financial investors. Hy24, which terms itself the world’s largest clean-hydrogen private equity asset manager, and COFIDES, Spain’s public-private financial entity, own a combined 29%, and Spanish renewable gas firm Enagás Renovable and solar developer Alter Enersun have a 20% share.
The project has EU and national backing. According to Moeve’s own announcement and project reporting, Onuba has been designated a Project of Common Interest by the European Commission and has secured roughly €304 million from the Spanish government under the Recovery, Transformation and Resilience Plan, financed through the EU’s NextGenerationEU programme. Together, these projects will make Palos de la Frontera home to Europe’s largest green-molecules energy hub and a benchmark for industrial transformation, with two of the four largest industrial projects currently under construction in Spain.
At a glance
| Item | Detail |
|---|---|
| Project | Onuba, phase 1 of Andalusian Green Hydrogen Valley |
| Developer | Moeve (51%), with Hy24, COFIDES, Enagás Renovable, Alter Enersun |
| Location | Palos de la Frontera, Huelva, Spain |
| Capacity | 300 MW electrolysis, expandable to 405 MW |
| Planned output | 45,000 tonnes green hydrogen per year |
| Investment | $1.2 billion (over €1 billion) for phase 1; $3.3 billion full valley plan |
| Status | Construction under way, reported 14 October 2026 |
Onuba’s 300 MW electrolyser scale puts it among the larger green hydrogen plants moving into construction in Europe this year, alongside other projects such as Shell’s Holland Hydrogen 1 in Rotterdam, a 200 MW plant nearing completion, and BASF’s 54 MW unit in Ludwigshafen, Germany.

What to watch
Onuba’s path to full operation will test whether a Project of Common Interest tag and hundreds of millions of euros in EU and Spanish subsidy can keep a hydrogen project of this scale on schedule and cost, at a time when several European electrolyser projects have faced delays or scaled-back ambitions.
Sources
- Source: Green Hydrogen Project Set to Be Europe’s Largest Starts $1.2B First Phase (Engineering News-Record)
- Source: Moeve launches Europe’s largest green hydrogen project (Moeve)
- Source: Moeve launches construction of the first phase of Europe’s largest green hydrogen project (Hydrocarbon Processing)
- Source: Southern Europe’s Largest Green Hydrogen Plant Reaches Final Investment Decision (JPT)
- Source: Shell Nears Launch of Estimated $1.17B Holland Green Hydrogen Project (Engineering News-Record)