Two grid systems on opposite sides of the Atlantic sent the same signal this month. In Great Britain, the cost of keeping the lights on hit records several days running. In the mid-Atlantic United States, the federal government ordered an emergency response to keep PJM’s system from running short. Neither event was caused by a shortage of power plants. Both were caused by networks that cannot move power to where it is needed, fast enough, when it is needed.
Britain’s grid strain, in numbers
In September the UK paid a record of just over half a billion pounds to balance its power system, according to data compiled by LCP Delta, and October could prove even more expensive, with actions taken on one day alone costing £38.4 million, a single-day record. That record did not last. The National Energy System Operator paid an estimated £49 million in balancing costs on the following Wednesday, a second consecutive day of record-breaking payments, after paying out £39.4 million the day before.
The UK’s electricity grid saw a 25% jump in payments to balance supply and demand so far this year, with the National Energy System Operator spending £2.1 billion for services including boosting generation in some parts of the country while dialing it down in others, according to data for January to September. That builds on a longer trend: the cost of balancing Britain’s electricity grid more than doubled to £11.8 billion between September 2021 and April 2025, twice the £5.08 billion consumers paid in the preceding 41 months.
The mechanism behind the headline figures is specific. Wind and hydroelectric power plants with a combined capacity of around 9 gigawatts were paid not to generate electricity on the day the £47.9 million record was set, a volume the consultancy estimates would have been enough to power more than 8 million typical households. Instead, the operator had to pay to bring gas and biomass plants online and buy more electricity from Europe via high-voltage subsea cables, with constraints most often affecting wind farms in Scotland, where there are insufficient high-voltage lines to carry generated electricity to areas of higher demand in the south. The system was even forced to ask for help from outside its borders: there were no major plant failures or extreme weather, and plenty of wind power was being generated in Scotland, but bottlenecks on the network meant not enough electricity could reach London and southeast England, forcing emergency action to secure additional imports from France.
Forecasts suggest this gets worse before it gets better. Balancing costs hit a record £505 million in September, and the annual bill is set to grow from an estimated £2 billion this year to £8 billion by 2028. Separately, Guardian reporting on the same data put the coming year’s bill at £505 million in September alone, the highest monthly figure on record, with costs expected to amount to £3.2 billion over the next year.
| Period | GB balancing cost | Context |
|---|---|---|
| April 2018 to August 2021 (41 months) | £5.08 billion | Pre-energy-crisis baseline |
| September 2021 to April 2025 | £11.8 billion | More than double the prior period |
| January to September 2025 (9 months) | £2.1 billion | Up 25% year on year |
| September 2026 (1 month) | £505.7 million | Record monthly high |
| 14 October 2026 (1 day) | £38.4 million | Single-day record at the time |
| 15 October 2026 (1 day) | ~£49 million | Record broken the next day |
Why wind in Scotland gets switched off while gas fires up in England
The explanation offered by the industry’s own analysts is blunt. Shivam Malhotra, head of power trading at LCP Delta, said the system overall wasn’t tight in terms of power supplies, calling it the age-old story of a lack of infrastructure to transport power to where it’s needed, leading to lots of wind farms being turned off. NESO itself points to the same fix. A spokesperson said the single biggest opportunity to reduce balancing costs is the timely delivery of new infrastructure by transmission owners, which could halve balancing costs by the end of the decade. The UK has three monopoly transmission networks, and the pace of their build-out, chiefly the lines needed to carry Scottish wind power south, has not kept up with the pace of wind farm connections.
The wider context matters for interpretation. Great Britain’s £150 billion power networks upgrade is not keeping pace with increasing renewable energy generation, underlining concerns over the pace of that programme as new renewable projects keep connecting to the grid. A likely reading is that the UK is now paying, in real time, for a sequencing problem it chose when it allowed generation connections to outrun transmission reinforcement. The bill lands on consumers either way: balancing costs are included in household energy bills.
The same story, a different grid: PJM’s emergency order
Four days before Britain’s second record balancing day, the US Department of Energy issued its own emergency order, for different proximate reasons but a related underlying one. On 12 October, Secretary of Energy Chris Wright issued an emergency order to 13 states and Washington, D.C., saying there was a significant risk of emergency conditions that could jeopardize electric reliability and public safety. The order covers Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, West Virginia and Washington, D.C., and works by authorizing backup generators and delaying planned maintenance on existing generators.
The trigger combined weather and demand growth. Autumn is normally a maintenance period for power grids because mild weather means less demand for climate control, but the Mid-Atlantic faced a record heatwave for October, meaning buildings used significantly more electricity than normal and risked overloading the grid. The margin was thin: DOE said PJM was forecast to be within 900 megawatts of its reserve margin on 14 October, with anticipated generation outages reaching 61,591 MW across PJM, most acutely in the BGE, PEPCO and Dominion zones. DOE estimates more than 35 gigawatts of unused backup generation remains available nationwide that could, in theory, be tapped.
PJM’s stress is not a one-off weather event layered on an otherwise comfortable system. It sits on top of a structural problem documented by the US Department of Energy’s own national laboratory. Roughly 2,061 gigawatts of capacity, 1,312 GW of generation and 749 GW of storage, was actively seeking interconnection at the end of 2025, with natural gas capacity up 86% while solar, storage and wind each fell around 16 to 19%. Projects that became operational in 2025 spent an average of eight years in the queue waiting to connect, by one tally, while a separate Berkeley Lab figure put the median project built in 2025 at 61 months from interconnection request to commercial operations, compared with 36 months historically. New capacity, in other words, is queued up behind the grid itself, not behind a shortage of developers willing to build it.
| Resource (US active queue, end-2025) | Capacity (GW) | Year-on-year change |
|---|---|---|
| Solar | 773 | Down 19% |
| Storage | 749 | Down 16% |
| Natural gas | 253 | Up 86% |
| Wind | 220 | Down 19% |
| Total active queue | Over 2,060 | Down 10% |

The scramble for flexibility
If transmission build-out is slow and expensive almost everywhere, grid operators and regulators are leaning harder on the alternative: making demand and storage flexible enough to substitute for wires. Three moves this month illustrate the pattern.
First, battery deployment keeps accelerating. Around 20.4 GWh of grid-scale battery storage came online globally in September, bringing the year-to-date total to 208 GWh, figures that are 61% and 43% higher respectively than the equivalent periods in 2025. China accounted for almost two-thirds of the September figure, commissioning over 12 GWh, while Europe installed over 2 GWh for a fifth consecutive month, taking its first-nine-months total to 22 GWh, up 182% year on year.

Second, France is rewriting connection rules to make hybrid solar-plus-storage projects easier to build. The government plans to facilitate deployment of medium-sized solar plants paired with battery storage by raising the maximum project capacity from 17 MW to 25 MW by year-end, provided grid injection does not exceed 17 MW. The change sits inside a broader push: government spokesperson Maud Bregeon unveiled additional measures aimed at accelerating electrification and improving electricity demand flexibility, identifying significant untapped potential in smart management of heating, domestic hot water and EV charging, which it estimates could cut associated energy costs by up to 35%. Concretely, the government plans to make heat pump subsidies conditional on smart-control capability from 2027, saving households between €150 and €200 annually, and intends to work with industry so that EV chargers have smart-control functions enabled by default, including connectivity to the Linky smart meter network or automatic off-peak scheduling. The French regulator has flagged why this matters for connections specifically: wider use of flexible grid connections is becoming essential as solar and battery projects compete for limited network capacity, with storage connection queues now totalling 2.8 GW.
Third, demand-side flexibility is being extended to households that have historically been locked out of it. A new project from E.ON Next and the technology firm Allume aims to let social housing tenants in flats share rooftop solar generation and get paid for supporting the grid, according to the companies, though the commercial terms and scale of that scheme were not detailed in available reporting.
Who gains, who loses
Gas plant operators located close to demand centres are clear near-term winners from Britain’s constraint payments: they are paid premium rates to fire up precisely when wind is being curtailed elsewhere. Battery storage developers and flexibility aggregators gain too, since every pound spent re-dispatching generation is, in principle, a pound that storage sited closer to demand, or demand that can shift in time, could capture instead.
Scottish wind generators are a more ambiguous case. They are paid to switch off rather than losing revenue outright, but curtailment payments do not deliver the clean electricity the system was built to use, and critics argue the arrangement reflects poor sequencing of grid investment rather than a working market. Consumers and businesses are the clearest losers in the UK case, since the costs, which are levied on to household energy bills, add to growing concerns over the pace of Britain’s £150 billion power networks upgrade. In the US, data centre operators and the wider economy benefit from DOE’s emergency authority keeping supply available through the autumn maintenance window, while nearby residents bear whatever reliability risk remains if a true shortfall materialises.
Competing views
The Nuclear Industry Association, in earlier analysis of the same UK data series, argued the high costs reflect Britain’s reliance on carbon-intensive gas, which sets the UK day-ahead power price 97% of the time, the highest in Europe, because Britain lacks alternative firm sources of power like nuclear, and used the figures to call for new baseload nuclear capacity. NESO’s own account places the emphasis differently, on the pace of transmission build rather than on the generation mix, arguing new infrastructure delivered by the transmission owners is the biggest lever available. Analysts at LCP Delta frame it as a transport problem rather than a supply or technology problem, pointing to the mismatch between where wind is generated and where demand sits. In the US, the DOE order was framed by the administration as a response to past policy: one official statement argued that past leaders’ energy subtraction policies have made the grid more vulnerable to the risk of blackouts when the sun doesn’t shine or the wind doesn’t blow, and said the administration remains committed to using every available tool to prevent blackouts, while PJM’s own public position was more measured, telling reporters it did not expect the emergency conditions to affect customers directly.
Risks and open questions
The UK’s own operator has effectively put a number on the prize: it says timely transmission delivery could halve balancing costs by the end of the decade, which implies the alternative path, continued delay, keeps bills elevated for years. Whether reinforcement projects between Scotland and England can actually accelerate enough to bend that cost curve is unresolved, and depends on planning consent, supply chains and financing that are largely outside NESO’s direct control.
On the US side, the open question is whether demand growth, led by data centres and electrification, will keep outpacing both new generation and the queue of projects waiting to connect. The headline figure of over 2,060 GW of active queue capacity is several times the installed generating capacity of the entire country, yet historically only a small fraction of queued capacity is ever built, so the queue is better read as a backlog of applications than a reliable pipeline of future supply.
A further uncertainty is whether flexibility measures, batteries, smart EV charging, flexible connections, can scale fast enough to substitute materially for new wires and reserve margin, rather than simply supplementing them at the margins. France’s regulator is explicit that flexible connections are becoming a condition of access rather than an optional extra, which suggests the direction of policy travel, but the scale needed to meaningfully offset transmission bottlenecks in systems as large as Great Britain’s or PJM’s remains unproven.
What to watch
- Whether NESO’s winter balancing costs, due to be reported in the coming months, extend the record run set in September and October 2026.
- Progress on the UK’s Scotland-to-England transmission reinforcement projects, and whether delivery timelines are pulled forward in response to the cost pressure.
- Whether PJM’s reserve margins tighten further heading into winter 2026, and whether further Section 202(c) emergency orders are issued.
- The next Lawrence Berkeley National Laboratory interconnection queue update, for signs of whether FERC Order No. 2023 reforms are shortening the multi-year wait for new generation and storage.
- Whether France’s 25 MW connection threshold and smart-control mandates for heat pumps and EV chargers are finalised and adopted on schedule by year-end.
Sources
- Source: UK Spends £2.1 Billion to Balance Power Grid as Renewables Surge – Bloomberg
- Source: The UK Is Paying More Than Ever to Steady a Straining Power Grid – Bloomberg via Energy Connects
- Source: Consumers Pay £12 billion to Balance Britain’s Power Grid as Costs Double – Nuclear Industry Association
- Source: Grid operator spends £50m in a single day to keep the lights on
- Source: Grid balancing cost hit record monthly high of £505 million in September – Utility Week
- Source: Cost of balancing Great Britain’s power grid reaches nearly £50m a day – AOL
- Source: Cost of balancing Great Britain’s power grid reaches nearly £50m a day
- Source: Feds issue emergency order over power grid concerns for 13 states – Virginia Business
- Source: Energy Secretary Chris Wright declares power grid emergency across 13 Mid-Atlantic states – Moneywise via Yahoo Finance
- Source: Order No. 202-26-2 PJM – US Department of Energy
- Source: 20.4GWh grid-scale BESS deployed globally in September, up 61%; YTD installs up 43% – Energy-Storage.News
- Source: Queued Up: 2026 Edition – Lawrence Berkeley National Laboratory
- Source: The US interconnection queue is twice its installed capacity – Latitude Media
- Source: France to ease grid connection rules for solar-plus-storage projects up to 25 MW – pv magazine Global
- Source: France eases grid connection rules for solar-battery projects – Montel
- Source: French regulator highlights flexible grid connections, battery queue pressures – pv magazine Global