China starts building phase 2 of world’s largest green ammonia site

State-owned China Energy Engineering Corporation (CEEC) began construction on 20 October 2026 of the second phase of its Songyuan green hydrogen-ammonia-methanol complex in Jilin province, northeast China, a project the company says will triple the site’s annual green ammonia output.

The Songyuan project, also referred to by CEEC as “Qing Hydrogen No.1,” has been operating its first phase since late 2025. That phase uses alkaline electrolysers powered by a dedicated 800 MW of wind and solar capacity to produce 45,000 tonnes of green hydrogen a year, which is converted into 200,000 tonnes of green ammonia, according to CEEC’s own project disclosures reported by industry outlet Ammonia Energy.

Phase 2 adds 630 MW of new capacity and, according to project figures cited by Construction Review Online, will cost 10.83 billion yuan ($1.62 billion). The expansion is expected to double the site’s total renewable generation capacity to 1,600 MW and lift annual green ammonia production to 600,000 tonnes. CEEC also expects the new phase to cut unit production costs by more than 10% compared with phase 1, through upgraded domestic equipment and digital plant management.

Hydrogen Insight reports that CEEC is targeting offtake in Korean and EU markets for the expanded output. Belgian shipping company CMB.Tech already holds an offtake agreement for green ammonia from the completed first phase and has expressed interest in volumes from phase 2, according to Hydrogen Insight’s reporting.

The full build-out at Songyuan is planned to eventually reach 3,000 MW of renewable generation and a combined 800,000 tonnes a year of green ammonia and methanol, per CEEC’s project scope. Songyuan sits alongside a wave of large Chinese state-backed hydrogen and ammonia projects reaching construction this year, including China Huadian’s $620 million facility in northeast China and a 2.6 billion dollar complex in Inner Mongolia.

At a glance

Item Detail
Developer China Energy Engineering Corporation (CEEC)
Location Songyuan, Jilin province, China
Phase 2 investment 10.83 billion yuan ($1.62 billion)
Phase 2 new capacity 630 MW electrolysis; total site renewables to reach 1,600 MW
Ammonia capacity 200,000 t/yr (phase 1, operating) rising to 600,000 t/yr (phase 2)
Status Phase 2 construction started 20 October 2026

What to watch

Whether CEEC can secure firm offtake contracts in Korea and the EU for phase 2 volumes, and whether the promised 10% cost reduction materialises once the expanded plant is commissioned.