The Midcontinent Independent System Operator (MISO) selected a consortium of Ameren Transmission Company of Illinois (ATXI), GridLiance Heartland and Dairyland Power Cooperative on 22 October 2026 to build a 765 kV transmission project in Iowa, with a MISO-estimated cost of about $1.23 billion.
| Item | Detail |
|---|---|
| What | EASL project: about 187 miles of 765 kV line, a 345/765 kV substation (East Adair) and about 22 miles of 345 kV lines |
| Who | ATXI (Ameren) and GridLiance Heartland (NextEra Energy Transmission), with Dairyland Power Cooperative |
| Where | Iowa, from southern Iowa north to the Minnesota/Iowa state line |
| Cost | About $1.23 billion (MISO estimate) |
| Status | Developer selected. Target in service: 1 June 2032 (345 kV), 1 June 2034 (765 kV), subject to regulatory approvals |
Context
The project is formally the East Adair–Minnesota/Iowa State Line–Arbor Hill–York Avenue line. Daily Energy Insider reports that it is a key part of a new 765 kV backbone for the Midwest.
ATXI and GridLiance will lead development. On completion they will own the line jointly with Dairyland, at stakes of 42.5%, 42.5% and 15%.
What is new
This is a competitive award. According to the companies’ joint release, MISO chose the group after judging that its proposal gave the best overall value, based on design, execution capability, regulatory experience and other factors.
ATXI chairman and president Shawn Schukar said the selection reflects a commitment to delivering value for customers. Dairyland CEO Brent Ridge said in the same release that the project will improve resilience and add flexibility for future energy resources and economic growth. These are the companies’ own claims.
Why it matters
765 kV lines carry far more power over long distances than the 345 kV circuits common in the region. Awarding the Iowa segment fixes the builders and the ownership split, which lets state permitting and detailed design begin. The in-service dates remain targets until regulators sign off.
What to watch
Watch for the consortium’s state siting and route filings in Iowa, and for any MISO cost updates as design work starts.
Sources
- Source: MISO selects consortium of Ameren, GridLiance, Dairyland to deliver foundational energy grid project in Iowa (NextEra Energy)
- Source: Ameren Corporation release on the MISO selection
- Source: Midcontinent ISO Selects Consortium for Major Iowa Transmission Project (APPA)
- Source: ATXI-GridLiance-Dairyland Power consortium will spearhead $1.23B Iowa transmission project (Daily Energy Insider)