ArcelorMittal partners finish first phase of Ghent capture trial

ArcelorMittal, Mitsubishi Heavy Industries (MHI), BHP and Mitsubishi Development Pty Ltd (MDP) said on 28 October 2026 that they have completed the first phase of a pilot carbon capture trial at ArcelorMittal’s Ghent steelworks in Belgium, capturing more than 90% of CO2 from blast furnace gas.

At a glance

Item Detail
What Phase 1 of a pilot carbon capture trial, pilot scale
Who ArcelorMittal (host), MHI (technology), BHP and MDP (financial partners)
Where Ghent integrated steelworks, Belgium; two blast furnaces, about 5 million tonnes of crude steel a year
Result (company claim) Capture rate above 90% over more than 4,500 hours of operation
Status Phase 1 complete (28 October 2026); phase 2 started

What the trial tested

The pilot used MHI’s Advanced KM CDR Process on pre-combustion blast furnace gas, according to the Association for Iron & Steel Technology. An MHI executive said the run covered gas containing dust, sulphur compounds and other impurities. The four parties first announced the multi-year collaboration in October 2022, per MHI.

Our calculation: 4,500 hours ÷ 24 hours per day = 187.5 days, or about six months of round-the-clock operation.

What the numbers mean for Ghent

Eurometal reports that, according to the companies’ engineering assessments, applying the technology at full scale to the blast furnace’s pre-combustion off-gas could lower the site’s overall CO2 intensity by up to 24%. Phase 1 separated only CO2. The remaining carbon monoxide could still be burned for power and heat on site, which releases more CO2, the companies said.

GMK Center notes the partners acknowledge that capturing a single stream does not resolve the plant’s total emissions. Phase 2 therefore moves to post-combustion gases from the hot strip mill’s reheating furnace, where gas conditions vary more, and is meant to inform capture across several emission points at once.

The trial’s stated aim, per Carbon Herald, is to test whether capture can be added to existing blast furnace sites. The statement describes data to support further assessment, not a commercial-scale project.

What to watch

Phase 2 results on reheating-furnace gas, and whether the partners move to a commercial-scale design for Ghent. The sources reviewed give no timeline or investment decision.