T1 Energy signs 1.58 GW of TOPCon module offtake deals

US manufacturer T1 Energy announced on 30 October 2026 that it has signed new offtake deals totaling more than 1.58 GW of solar modules, with deliveries planned for 2027 and 2028 from its Texas module plant.

According to the company’s press release, the contracts include deals with subsidiaries of independent power producer Avantus. The TOPCon (tunnel oxide passivated contact) modules will come from T1’s 5 GW G1_Dallas assembly plant. PV Tech reports that the modules will use a mix of imported cells and domestically produced cells from G2_Austin.

Cell fab still under construction

G2_Austin, in Milam County, Texas, began construction in December 2025. The first phase, at 2.1 GW, is expected to start producing cells in the first quarter of 2027, according to the company. Until then the domestic-cell share of these deliveries is a plan, not output.

T1 says it now has more than 4 GW of its 2027 module manufacturing capacity under contract. Our calculation: if “2027 capacity” equals the 5 GW G1_Dallas nameplate, 4 GW ÷ 5 GW = at least 80% is sold. The company has not stated that base, so treat the ratio as indicative.

Why it matters

The deals show US developers contracting for modules tied to a domestic supply chain well ahead of delivery. T1 says it also acquired foundational TOPCon patents and other intellectual property in July. Contract prices and the split between imported and domestic cells were not disclosed in the sources reviewed.

Item Detail
Announced 30 October 2026
Who T1 Energy; buyers include Avantus subsidiaries
Size More than 1.58 GW of TOPCon modules
Supply source G1_Dallas, Texas (operating, 5 GW)
Delivery 2027 and 2028

What to watch

Whether G2_Austin’s first 2.1 GW phase starts cell production in the first quarter of 2027, as T1 expects. The share of domestic cells actually delivered under these contracts will follow from that.

Sources