The US energy storage industry installed 14.3 GWh in the third quarter of 2026, taking installations for the first nine months to 48.3 GWh, according to the Q4 2026 US Energy Storage Market Outlook from the Solar Energy Industries Association (SEIA) and Benchmark Mineral Intelligence, released on 17 November 2026. That is 20% more than the same period of 2025, and it lifts cumulative US installations above 200 GWh.
What the data shows
SEIA splits the nine-month total into 40.8 GWh of utility-scale systems and 7.5 GWh behind the meter (commercial, industrial and residential). In the third quarter alone, utility-scale projects supplied 12.2 GWh across 45 projects, commercial and industrial (C&I) systems 1.3 GWh and residential systems 746 MWh, POWER reports.

Source: SEIA/Benchmark Mineral Intelligence, US Energy Storage Market Outlook Q4 2026
Texas led utility-scale deployment through the third quarter with 12.3 GWh, followed by Arizona with 7.7 GWh and California with 6.8 GWh, per the same report. SEIA also says 11 states had already beaten their previous full-year installation records by the end of September: Colorado, Massachusetts, Utah, Michigan, Georgia, Mississippi, Virginia, Iowa, Montana, Alabama and Illinois.

Source: SEIA/Benchmark Mineral Intelligence, as reported by POWER, 17 November 2026
The quarterly path was uneven. The previous SEIA edition recorded 20.2 GWh in the second quarter, which it called an all-time record, so the 14.3 GWh in the third quarter is lower. First-quarter installations were put at 9.7 GWh, up 32% year on year, by Facilities Dive’s account of the May report. Earlier editions are revised as projects are confirmed, so quarter-on-quarter comparisons across editions are unreliable.
| Measure | Value | Period | Source |
|---|---|---|---|
| US installations (GWh) | 48.3 | Q1 to Q3 2026 | SEIA/Benchmark |
| Year-on-year change (%) | 20 | Q1 to Q3 2026 | SEIA/Benchmark |
| Utility-scale (GWh) | 40.8 | Q1 to Q3 2026 | SEIA/Benchmark |
| Behind the meter (GWh) | 7.5 | Q1 to Q3 2026 | SEIA/Benchmark |
| 2030 cumulative forecast (GWh) | 708 | Forecast to 2030 | SEIA/Benchmark |
| Storage additions forecast (GW) | 383 | 2026 to 2036 | BloombergNEF |
The forecasts moved up
SEIA and Benchmark now forecast cumulative US deployment of 708 GWh by 2030, a 3.7% increase on the 683 GWh Energy-Storage.News cited from their earlier-in-the-year edition. RTO Insider, covering the same outlook, headlines a projected 74 GWh gain for 2026.
BloombergNEF (BNEF) is more bullish still. Its latest outlook expects 383 GW of US storage additions from 2026 to 2036, up 34% from its May 2026 outlook. Utility Dive summarised the revision as roughly 30%, so the exact uplift depends on how it is measured.
BNEF attributes much of the change to data centres. It says hyperscalers’ interest in on-site and nearby storage has turned into firm orders, with 4.9 GW/7.4 GWh of on-site data-centre storage expected in 2026, up from 500 MW/1.4 GWh in 2025. Those are BNEF’s projections, not installed data.
Who gains
Utility-scale developers and the utilities that buy from them gain most, simply because they account for the bulk of the volume. The SEIA data page also credits falling system costs, demand for reliable power and federal and state incentives for the growth.
Commercial and industrial storage is a smaller winner. SEIA reports 1.3 GWh in the third quarter and 1.8 GWh in the second, and Energy-Storage.News describes data centres as breathing life into a segment that has been the weakest. Residential is the soft spot: SEIA-Benchmark predict 3 GWh of home batteries in 2026, a decline of 8% from 2025, though that is milder than many expected.
Ratepayers may also gain, according to SEIA. The association says growth in solar and storage helped cut average wholesale electricity prices by 42% in Texas and 51% in California between summer 2021 and summer 2026. That is SEIA’s own analysis from an industry body, and the figures do not isolate storage from solar, gas prices or demand.
Who is squeezed
Projects that rely on Chinese cells face tougher rules. Foreign-entity-of-concern (FEOC) restrictions and a higher Section 301 tariff on Chinese-origin batteries both took effect on 1 January 2026, Energy-Storage.News reported, a market where about 75% of US lithium-ion battery imports come from China. The FEOC test requires non-prohibited-entity content of at least 55% for storage projects starting construction in 2026, rising to 75% for projects starting in 2030 or later, according to a summary of IRS Notice 2026-15.
Estimates of the tariff burden differ by date and method. Energy-Storage.News put combined tariffs on Chinese batteries and storage systems at around 55% from 1 January 2026, while BNEF now cites a combined duty of 40.9% on stationary storage batteries from mainland China. The sources do not explain the gap, and the difference may reflect later changes in tariff rates.
Smaller developers face particular risk. The consultancy Teneo, writing earlier, warned that small and mid-sized developers unable to buy at scale ahead of 2026 or to contract FEOC-compliant supply afterwards could face delays, renegotiated contracts and liquidity strain. BNEF adds that restrictions on foreign-made inverters and other bulk-power equipment weigh on project economics, although projects with tax credits can still absorb higher costs.
Can domestic supply keep up?
SEIA’s data page lists 92.4 GWh of US manufacturing capacity operating and over 109.6 GWh of battery pack manufacturing online. Plants in Tennessee and Indiana recently opened, according to a trade-press summary of the report, and several EV battery lines are being converted to storage cells.
S&P Global‘s outlook from late 2025 compared 58 GWh of expected 2026 storage demand with 37.25 GWh of annual US lithium-iron-phosphate cell capacity available for storage. In 2025, Wood Mackenzie projected that domestic manufacturing would meet 6% of then-current demand and 40% of expected 2030 demand, so imports would be needed for years. These are forecasts from different dates and definitions, but they point the same way: US factories are growing, yet not at the pace of installations.
New York tests the state-level model
On 12 November 2026, the New York State Energy Research and Development Authority (NYSERDA) opened its second Bulk Energy Storage solicitation, seeking about 1 GW. The programme aims at 3 GW of bulk storage over at least three annual rounds, within a statewide goal of 6 GW by 2030. Energy-Storage.News notes that “bulk” means projects of 5 MW or more, and that a third round is due in 2027.
Developers bid for Index Storage Credits, which NYSERDA says pay out only after a project has been permitted, built and passed inspections. News10 reports that at least 20% of the capacity awarded must be able to discharge for at least eight hours. Separately, at least 35% of NYSERDA-supported off-site storage is planned for downstate New York.
The first round drew bids for 46 eligible projects totalling roughly 6 GW and 30 GWh, and NYSERDA contracted eight projects totalling 950 MW.
Our calculation: 6,000 MW bid ÷ 950 MW contracted = 6.3, so the first round was about six times oversubscribed on power capacity (rounded; the 6 GW is NYSERDA’s “roughly” figure).
Energy-Storage.News adds that stringent fire codes are among the other significant barriers in the state. Local opposition is a live issue elsewhere in the Northeast too: residents in Hadley, Massachusetts, have urged the town Board of Health to oppose a battery site on a hill, according to the Daily Hampshire Gazette. Whether the proposal is approved is not settled in the reporting available.
Competing readings
The industry reading, from SEIA, is that the 20% rise shows storage is delivering lower costs and reliability, and it urges Congress to pass the Bipartisan American Affordability and Jobs Act of 2026 (BAAJA), according to POWER. SEIA is a trade body for solar and storage developers, so the framing favours expansion.
A more cautious reading comes from the trade-policy side. Analysts quoted by Energy-Storage.News say FEOC rules and tariffs are pushing developers toward domestic or non-Chinese supply at higher initial cost, with Arevon Energy’s chief operating officer Justin Johnson describing them as an added impetus for domestic supply. BNEF’s own wording is that protectionism adds risk to its outlook even as tax credits keep building.
A likely reading of the data: the nine months of 2026 mostly reflect projects that were safe-harbored or financed before the new rules bit. Several analyses describe developers rushing to secure inventory ahead of the 1 January 2026 changes, and SEIA says developers safe-harbored large volumes of solar. If that is right, the true test of the FEOC regime comes in 2027 and 2028 installations, which this report cannot yet show. This is interpretation, and the sources do not quantify the share of 2026 projects that were safe-harbored.
Risks and open questions
- Policy durability. Federal storage tax credits run to 2033 or later by different descriptions (Energy-Storage.News says 2033; BNEF says eligibility extends through 2035). Rules on tariffs and FEOC guidance are still being issued on a rolling basis.
- Grid access and permitting. The 20% growth was achieved while interconnection and local siting remain contested, as in New York’s fire-code rules and in Hadley.
- Measurement. Trackers such as SEIA/Benchmark and Wood Mackenzie/American Clean Power Association use different methods, and SEIA’s own pages cite both “over 200 GWh” and 215 GWh for cumulative capacity.
What to watch
The first date is 15 December 2026, when step-one eligibility applications for the NYSERDA solicitation fall due, according to the programme’s published schedule as reported by mGrid. The number of bids relative to the first round’s 6 GW will show whether developers still see value in the Index Storage Credit model.
Next come the fourth-quarter installation figures, expected in the next SEIA/Benchmark edition, and the proportion of projects built with FEOC-compliant supply. A Congress change in January, which SEIA links to the midterm elections, may also alter the legislative debate over tariffs and credits, though no bill outcome is known as of 17 November 2026.
Sources
- SEIA: REPORT: U.S. Exceeds 200 GWh of Energy Storage Capacity Installed to Date
- SEIA: Energy Storage Market Outlook Q4 2026
- SEIA: Energy Storage Market Outlook Q3 2026
- SEIA: Solar and Storage Industry Research Data
- NYSERDA: Bulk Energy Storage Solicitations
- BloombergNEF: US Clean Power Rises With Data Centers: Three Things to Know
- POWER: U.S. Exceeds 200 GWh of Installed Energy Storage Capacity
- RTO Insider: U.S. Surpasses 200 GWh of Storage; 74 GWh Gain Projected for 2026
- Energy-Storage.News: US energy storage deployments for first nine months of 2026 up 20% from last year
- Energy-Storage.News: New York launches second annual 1GW ‘bulk’ energy storage solicitation
- Energy-Storage.News: EV slowdown as lifeline for US energy storage amid FEOC, tariffs
- Utility Dive: BNEF ups US energy storage deployment forecast by 30%
- Facilities Dive: US energy storage installations hit Q1 record, up 32% year over year
- Norton Rose Fulbright Project Finance: New FEOC Guidance: Notice 2026-15
- American Public Power Association: New York Agency Issues Bulk Energy Storage Solicitation
- News10: New York opened bidding for 1 GW of batteries as winter threatens power grid
- mGrid: NYSERDA’s Second 1GW Bulk Energy Storage Solicitation Sets Dec. 15 Eligibility Deadline
- S&P Global Market Intelligence: US renewables, battery sectors face new supply chain restrictions in 2026
- Utility Dive: Tariffs to spike power generation costs: reports
- Teneo: OB3’s Impact on U.S. Energy Storage
Header image: official press image from seia.org.