The US Department of Energy said on 16 October 2026 that it intends to deploy up to $50 million in Defense Production Act funding to expand transmission capacity in Virginia and West Virginia, backing a project led by Virginia Energy with utilities Appalachian Power and Potomac Edison.
Virginia Energy’s Grid Enhancing Technologies for Virginia & West Virginia Large Load Growth project will receive up to $50 million in DPA funding to deploy advanced transmission technologies along existing transmission corridors, adding an estimated 290 megawatts of transmission capacity across Appalachian Power’s Virginia system, one to four years faster than conventional transmission upgrades. The work pairs advanced reconductoring, which replaces existing wires with higher-capacity conductors, with dynamic line rating, which uses real-time operating conditions to determine how much electricity transmission lines can safely carry, according to the department.
Existing wires, not new corridors
DOE officials framed the approach as squeezing more capacity from the grid already in place. “A stronger electric grid doesn’t always mean building more power lines. Sometimes it means making better use of the ones we already have,” said Katie Jereza, assistant secretary of DOE’s Office of Electricity. A DOE spokesperson told Latitude Media that the objective is to expand transmission capacity, improve reliability, and reduce congestion in Virginia and West Virginia by upgrading existing infrastructure rather than building entirely new transmission corridors.
Energy Secretary Chris Wright announced the grant at an Appalachian Power substation near Lynchburg, Virginia, alongside Congressman John McGuire and Appalachian Power’s president, Brian Abraham. The federal grant is matched by Appalachian Power, bringing the total project cost to $100 million over a 48-month timeline, and construction is slated to begin in the summer of 2028 and conclude by the summer of 2030, though the utility told a local broadcaster it expects work to start sooner, within the next two years.
The money comes from a separate pool than DOE’s better-known grid program. Until now, DOE had largely relied on a program enacted under the Biden-era bipartisan infrastructure law, rebranded as SPARK by the Trump administration, which awarded $1.9 billion to 31 projects in late September; that law only authorized funding through fiscal 2026. Last year, the GOP’s One Big Beautiful Bill appropriated $1 billion under the DPA for energy infrastructure the administration deems critical to national security, under Presidential Determination No. 2026-10, which identifies transmission lines and conductors, substations, and power-control and protection equipment as essential to national defense. This Virginia-West Virginia award is one of the first substantial uses of that pot; Latitude Media reports transmission investments from it have so far totaled $200 million, including a similar DPA-funded transmission project in Alaska.
The push comes against a backdrop of rising load growth across PJM, the regional grid operator spanning 13 states and the District of Columbia including Virginia and West Virginia. A separate federal transmission study, cited by the West Virginia Science and Technology Policy Initiative, found PJM needs to grow its internal transmission capacity by 60% and its connections with external transmission grids by 500% by 2035 to meet forecasted demand. Reconductoring projects like this one are positioned as a faster, cheaper alternative to new high-voltage lines, which can take a decade or more to permit and build.
| Item | Detail |
|---|---|
| What | Reconductoring and dynamic line rating on existing transmission lines |
| Who | Virginia Energy, Appalachian Power, Potomac Edison; funded by US DOE |
| Where | Virginia and West Virginia (PJM footprint) |
| Size | Up to $50 million DPA funding, $100 million with utility match; ~290 MW added capacity |
| Status / date | Announced 16 October 2026; 48-month project, construction targeted 2028-2030 |

What to watch
DOE has not yet detailed how the remaining balance of the $1 billion DPA energy pool will be allocated, or whether more reconductoring grants will follow in other PJM states facing similar data center-driven demand growth.
Sources
- Source: Energy Department Announces Virginia and West Virginia Transmission Project to Receive Defense Production Act Funding
- Source: DOE turns to defense funds to squeeze more from power grid (Latitude Media)
- Source: Energy Dept. to use Defense Production Act funding to expand transmission capacity in Virginia, West Virginia (Daily Energy Insider)
- Source: Grid Transmission (West Virginia Science and Technology Policy Initiative)
- Source: DOE Puts $50 Million in Defense Production Act Money Behind 290 MW of Reconductoring on Appalachian Power Lines
Header photo of Appalachian Power: George Campbell from Worthington, OH, USA, CC BY 2.0, via Wikimedia Commons.