South Korea opened its second offshore wind auction of 2026 on 30 October, offering about 2.2 GW of fixed-price contracts and taking the year’s tendered volume to roughly 4 GW. The Ministry of Climate, Energy and Environment also lowered the bid price ceilings, by 1.34% for fixed-bottom projects and 0.63% for floating ones, Seoul Economic Daily reports.
The round is the first since the ministry published a 10-year bidding roadmap on 30 June 2026. It matters because Korea is trying to move from a small base to one of the largest offshore wind pipelines in Asia, and each auction tests whether developers, turbine makers and regulators can keep pace. Offshore capacity stood at about 0.35 GW when the government set its targets in December 2025, according to The Korea Times.
What is on offer in the second-half round
The ministry is tendering about 1,700 MW of fixed-bottom capacity and about 500 MW of floating capacity, Offshore Wind (offshorewind.biz) reports. The fixed-bottom volume splits into about 1,400 MW in the general track and about 300 MW in the public-led track. Applications run from 30 October to 10 December 2026, with awards expected from December onwards, according to reNEWS, which cites the Global Wind Energy Council for the volume breakdown.
| Segment | First-half 2026 offered (MW) | Second-half 2026 offered (MW) | Change (MW) |
|---|---|---|---|
| Fixed-bottom, general | 1,000 | 1,400 | +400 |
| Fixed-bottom, public-led | 400 | 300 | -100 |
| Floating | 400 | 500 | +100 |
| Total | 1,800 | 2,200 | +400 |
Figures are approximate volumes as reported by reNEWS and offshorewind.biz on 30 October 2026.
The ceiling for fixed-bottom projects with a land-based grid connection is KRW 168,937/MWh, and for floating projects KRW 174,003/MWh, per reNEWS. In the first half the ceilings were KRW 171,229/MWh and KRW 175,100/MWh, according to a Norton Rose Fulbright country review (information correct as of July 2026).

Source: Splash247 and offshorewind.biz, reporting South Korea's Ministry of Climate, Energy and Environment results (late June 2026)
What the first-half round showed
The first-half auction drew bids for 3,656 MW from nine projects, and five projects totalling 1,786 MW were selected, the ministry said in results reported by Splash247. Of that, 1,254 MW was fixed-bottom, against 689 MW selected across all of 2025, and 532 MW was floating. The ministry told the press that awarding more than 1.2 GW of fixed-bottom capacity under a lower ceiling showed “the sector is continuing to mature”.
The ministry described the round as the first to reach a 2:1 competition ratio since the scheme began in 2022, according to offshorewind.biz. Ajupress reports a ratio of 3.75:1 for floating wind and 1.6:1 for fixed-bottom projects. Floating wind returned after no floating tender was held in 2025 because of low participation.
| Project | Capacity (MW) | Segment | Reported lead developers |
|---|---|---|---|
| Haewoori 2 | 532 | Floating | Copenhagen Offshore Partners, SK Group |
| Haesong 3 | 504 | Fixed-bottom, general | Copenhagen Offshore Partners |
| Hanbit | 340 | Fixed-bottom, general | B.Grimm |
| Gulupdo | 250 | Fixed-bottom, general | Hanwha Group, SK Group (per Splash247) |
| Geumodo | 160 | Fixed-bottom, public-led | DL E&C, Korea Midland Power |
Projects selected in the first-half 2026 round, announced in late June 2026. Outlets differ on the Gulupdo consortium line-up.
The rules also changed. The first-stage cap that limited selection to about 120% to 150% of the announced volume was removed for the first half, according to a Lexology summary of the Korea Energy Agency notice. Evaluation still splits 50 points for the project proposal and 50 for price.
The price signal
The data shows a small cut. The fixed-bottom ceiling fell from KRW 171,229/MWh to KRW 168,937/MWh between the two rounds, and the floating ceiling from KRW 175,100/MWh to KRW 174,003/MWh.

Source: Norton Rose Fulbright (first half, July 2026); reNEWS and offshorewind.biz (second half, 30 October 2026)
A likely reading is that the ministry is using the better competition ratio to ratchet prices down in small steps while keeping them high enough to hold bidders. The ministry itself says the cut is meant to reduce generation costs gradually. Larger savings may come from contract length: Splash247 reports that officials are preparing to extend fixed-price contracts from 20 to 25 years, and Seoul Economic Daily says the next auction may adopt that term. The exact price effect is unresolved, an industry official told local media.
The 10-year pipeline behind it
The roadmap commits the government to auction 55 GW from 2026 to 2035, with annual volumes above 4 GW, according to Ajupress. The existing fixed-price auctions run until 2033, and a second track for designated development zones under the Offshore Wind Special Act begins in 2029. The government targets 25 GW of cumulative offshore wind by 2035, per The Korea Times.
Tendered capacity and built capacity are different things. Awards in 2026 add up to about 4 GW of tender volume, but none of the first-half winners has been reported as under construction in the sources reviewed here.
Who gains and who loses
Developers with awards gain revenue certainty. Copenhagen Offshore Partners holds two of the five selections, Haesong 3 and Haewoori 2, which together total 1,036 MW. Korean industrial groups such as SK, Hanwha and DL E&C appear in the winning consortia. Haesong 3 was not selected in the 2025 round, Asia Business Daily reported, when its plan used Vestas turbines.
Bidders that missed out lose time. Of the 3,656 MW bid in the first half, 1,870 MW (3,656 minus 1,786) went unselected. Whether those projects rebid in the second half is not stated in the sources reviewed.
Domestic suppliers gain from the scoring system. The ministry says the selected projects have committed to domestic suppliers for foundations, power cables, installation and operations. Foreign turbine makers without a local production route face the sharpest disadvantage.
Turbines, security and local content
The turbine question is the most contested part of the programme. In 2025, strengthened security scoring eliminated every private project using foreign turbines, while all public-led projects with Korean turbines were selected, Asia Business Daily reported.
The first-half 2026 results moved the line. Hanbit, which had failed in two earlier rounds partly because of its Chinese-linked turbines, was selected, Asia Business Daily reported. The developer plans 13.6 MW turbines assembled at a Korean plant under a licence from Vensys, a German-named company in which Goldwind of China holds 70%. The ministry said it would work with relevant agencies to verify security for turbines and control systems.
Views differ on how far to go. Some industry figures argue that Chinese equipment or 15 MW-class European turbines are needed to cut investment costs, a view Asia Business Daily says is common among overseas developers and financial institutions. Others say foreign turbines should come with local production and technology transfer, as in the Doosan Enerbility and Siemens Gamesa model. Korea had just completed a 10 MW demonstration turbine, while Vestas, Siemens Gamesa and Goldwind already sell 15 MW to 16 MW machines, according to the same report.
Security concerns have also reached construction. Korea’s main opposition People Power Party urged a review of two West Sea projects last year over Chinese involvement, The Investor reported. Asia Business Daily reported in June 2026 that Chinese vessels and technicians were installing turbines at the Nakwol project; the company said they do not conduct seabed surveys, and the ministry said it would run an additional security review at completion (Asia Business Daily).
Permitting is the slower clock
An analysis by Seoul Economic Daily, published on 16 October 2026, covered 13 large projects due for completion before 2030. It found an average of 113 months between the initial generation licence and completion. Construction took 24.4 months, and administrative steps such as environmental assessment and military reviews took 88.6 months.
Our calculation: 88.6 months of administration divided by 113 months in total is 78.4%, so roughly four-fifths of the average project timeline sat outside construction. The newspaper notes the real timeline is longer, because developers also had to measure wind for at least a year before applying.
The planned-siting regime under the Special Act is meant to shorten this. The Institute for Energy Economics and Financial Analysis (IEEFA) said in a September 2026 briefing that the Act appears designed to address project realisation problems, but its effect depends on whether government can speed approvals and settle disputes.
Risks and open questions
- Delivery pace. IEEFA says legacy development problems, shifting policy, localisation requirements and ambitious targets could erode developer and investor confidence. It also notes that overlapping auction and award processes through 2029 and 2030 expose developers to different risk profiles.
- Vessels and ports. In December 2025 Asia Business Daily reported that Mokpo New Port was the only port that could effectively support offshore wind, and the government planned more ports and installation vessels.
- Price versus localisation. Each local-content or security requirement can raise costs, while price carries half the evaluation score. How the ministry balances the two will show up in who wins.
- Contract terms. The 25-year contract change is reported as under consideration, not adopted.
What to watch
The bid deadline on 10 December 2026 and the volume of applications will show whether second-half competition matches the first half’s 2:1 ratio. Results, expected from December, will show whether the lower ceilings and the larger fixed-bottom volume still attract enough bids.
Further signals include a formal decision on 25-year contracts, the outcome of the ministry’s security checks on turbines and control systems, and whether the first-half winners secure financing and turbine supply on the announced timelines.
Sources
- Offshore Wind: South Korea Launches Second Offshore Wind Tender in 2026
- Seoul Economic Daily: Korea Expands Offshore Wind Auctions to 4GW, Lowers Price Caps
- reNEWS: South Korea launches 2.2GW offshore wind auction
- Splash247: South Korea awards nearly 1.8GW of offshore wind projects
- Offshore Wind: CIP Secures 1 GW Across Two Projects in South Korea’s Offshore Wind Auction
- Ajupress: South Korea Unveils 10-Year Roadmap for Offshore Wind Power Expansion
- The Korea Times: Korea to expand offshore wind power generation capacity by 11-fold by 2030
- Lexology: H1 2026 Auction for Korean Fixed-Price Wind Power Contracts
- Norton Rose Fulbright: Global offshore wind, South Korea
- Splash247: South Korea to stretch offshore wind price contracts to 25 years
- IEEFA: South Korean offshore wind success requires a public-private approach to project realization
- Seoul Economic Daily: China Builds Offshore Wind Farms in 4 Years; Korea Needs 10
- The Asia Business Daily: Five Offshore Wind Operators Selected in Auction
- The Asia Business Daily: Foreign Turbines Eliminated in Offshore Wind Power Bidding as ‘Security Scores’ Strengthened
- The Asia Business Daily: The Intensifying Large Turbine Battle
- The Asia Business Daily: Korea’s Largest Offshore Wind Farm Relies on Chinese Vessels and Technicians
- The Investor: Opposition party urges review of West Sea wind projects over Chinese ties
- The Asia Business Daily: Expanding Supporting Ports and Adding Installation Vessels
Header image: illustration, AI-generated.