Portugal mandates grid-forming for large batteries, opens 1 GW tender

Portugal’s government has made grid-forming capability and synthetic inertia mandatory for battery storage plants of 45 MW and above, with the rules in force from 23 October 2026, and has opened procedures to award about 1 GW (1,050 MVA) of grid capacity to storage projects.

The regulation took effect on 23 October 2026, TaiyangNews reports. SolarQuarter adds that plants of 500 kW or more must switch automatically from charging to discharging when grid frequency falls. pv magazine says Portugal is moving ahead of the EU’s own revision of generator connection requirements.

On the market side, Energía Estratégica reports that the government formalised two competitive procedures on 22 October 2026 for a maximum of 1,050 MVA. The procedures allocate injection capacity only, and the outlet notes this does not guarantee equivalent power to charge from the grid.

Energy-Storage.News reports that Portugal is targeting 6.9 GW of storage by 2030. Our calculation: 1,050 MVA ÷ 6,900 MW ≈ 15%. This is a rough comparison, because MVA measures apparent power and the target is in GW.

The same outlet says Sonnedix has put two solar-plus-storage projects into commercial operation in Portugal: Acail (28.3 MWp PV, 60.2 MWh battery) and Felgueiras (39.9 MWp PV, 80.3 MWh). Sonnedix says both operate in hybrid mode with “full grid charging capacity”, a term it did not define.

At a glance

Item Detail
Who Government of Portugal
Rule Grid-forming and synthetic inertia for battery plants of 45 MW and above
In force 23 October 2026 (adopted)
Procedures Two, for up to 1,050 MVA of injection capacity (opened 22 October 2026)

What to watch

Developers will want to see how the grid operator defines grid-charging limits under the procedures, and whether the EU’s connection-requirement revision follows Portugal’s approach.