US storage: import curbs, factory delays and a permitting vote

US battery storage developers are dealing with three pressures at once: a national-security order aimed at foreign-made batteries, manufacturing delays at a storage integrator, and a Senate permitting bill that more than 300 solar and storage companies want passed. Together they show where the US market stands on 10 November 2026.

What has happened since late August

The table lists the dated events that matter for US storage, with their status as of 10 November 2026.

Date (2026) Event Status
26 August Executive Order 14421 declares a national emergency over foreign-made bulk-power equipment, including battery energy storage systems Signed; DOE rules due within 120 days
16 September Fluence cuts its fiscal 2026 revenue outlook to about $2.4 billion Company guidance
28 September Shareholder class action filed against Fluence and two executives Allegations, not findings
30 September S. 5653, the Bipartisan American Affordability and Jobs Act, introduced in the Senate Proposed, not enacted
30 October to 2 November Fluence CEO and CFO depart; interim leaders named Searches for permanent successors under way
7 November Senate sponsors release a substitute text for S. 5653 Proposed amendment
9 November Cloture vote on S. 5653 scheduled Outcome not confirmed in the sources reviewed
24 December Deadline for DOE to issue rules implementing the order Pending

The import order: broad text, rules still to come

Utility Dive reports that President Donald Trump signed the order on 26 August 2026, blocking utilities from connecting some foreign-made equipment to the bulk power system, including transformers, batteries and inverters. The Department of Energy has 120 days to write the implementing rules, ESS News notes, which puts the deadline on 24 December.

Headlines called it a ban, but a law-firm analysis says transactions are not barred until the DOE determines that the equipment in question poses an unacceptable risk. The scope is wide. The order also covers uninterruptible power supply systems supporting critical infrastructure, according to Rystad Energy, which extends it to the backup batteries used at data centres.

The Inside Energy & Environment legal commentary adds that the DOE may examine software, firmware, remote-access capabilities and maintenance services as well as the hardware. A data centre operator buying a battery whose firmware comes from a subsidiary in a covered jurisdiction is one of its examples.

How exposed is storage?

Rystad Energy’s analysis finds that US reliance on Chinese transformers and inverters has already fallen substantially, so battery systems are the more exposed category. BloombergNEF analysts told Utility Dive that the battery sector faces more near-term risk than other industries and is likely to see delays and cancellations. Quartz reports that the International Energy Agency estimates China holds roughly 80% of global manufacturing capacity for batteries and solar inverters.

Critics exist. In an Energy-Storage.news analysis, Nicholas Weaver of the International Computer Science Institute in Berkeley argues that such bans harm US security rather than protect it. Energy-Storage.news also carries a case for the order from other commentators, who favour a blanket exclusion of equipment tied to a foreign adversary.

The security concern is not abstract for operators. Energy-Storage.news reports that the Huatacondo solar-plus-storage project in Chile has been offline for two months, with the operator’s log mentioning “cybersecurity”. The cause has not been confirmed in the sources reviewed.

A domestic supply test case: Fluence

The order assumes that supply can shift. Fluence Energy, a Nasdaq-listed storage integrator, shows how hard a domestic ramp-up can be, though the company has not linked its problems to the order.

The company’s initial fiscal 2026 revenue guidance was $3.2 billion to $3.6 billion, with a $3.4 billion midpoint, according to its first-quarter filing. In its third-quarter results, published in early August, it reported a record backlog of about $6.4 billion at 30 June 2026 and cut the revenue range to $2.9 billion to $3.1 billion. On 16 September, in a filing, it lowered the figure again to about $2.4 billion and projected an adjusted EBITDA loss of about $200 million. The company attributed the cut mainly to delays in ramping up its contract manufacturing facility in Houston.

Fluence fiscal 2026 revenue guidance midpoint. Revenue guidance midpoint: Initial guidance (reaffirmed in 2026) 3.4, Revised early Aug 2026 3, Revised 16 Sep 2026 2.4 (USD billion)
Fluence fiscal 2026 revenue guidance midpoint
Source: Fluence Energy filings and results releases (SEC Form 8-K, Fluence investor relations)

Our calculation: the guidance midpoint fell from $3.4 billion to $2.4 billion, a cut of ($3.4bn – $2.4bn) / $3.4bn = 29.4%. The backlog meanwhile rose, so the gap lies in delivery, not in orders.

Fluence contracted backlog. Backlog: As reported Nov 2025 5.3, 31 Mar 2026 5.6, 30 Jun 2026 6.4 (USD billion)
Fluence contracted backlog
Source: Fluence Energy results releases; Yahoo Finance report on the November 2025 results

Orders were strong in the same quarter. A Yahoo Finance summary of the earnings call puts record third-quarter orders at $1.44 billion and describes the $6.4 billion backlog as up 14% on the previous quarter. Fluence’s own filings caution that backlog may not turn into revenue in the period expected, or at all.

Management change and litigation

CFO Dive reports that Axel Meier, a board member and former Siemens finance executive, became interim CEO, and Ricardo Roizen, from AES, became interim CFO. They replaced Julian Nebreda and Ahmed Pasha, who stepped down on 30 October. A class action filed on 28 September names both men and alleges that the company misrepresented its manufacturing capabilities. Those are allegations; no court has ruled on them.

Fluence has said it is creating a board committee to oversee manufacturing and operations, according to Energynews. That outlet is a trade aggregator, so the company’s own filings remain the authoritative record.

Interpretation: one company’s execution problems do not describe the whole sector. A likely reading is narrower: when a large integrator with a record backlog struggles to bring a US contract manufacturing line up to speed, the premise that domestic capacity can quickly replace imported systems deserves scrutiny.

Others are trying. Energy-Storage.news carries a report that Ford Motor Company’s energy storage subsidiary, Ford Energy, will partner with developer DESRI to deploy storage in the US. Details were not available in the sources reviewed.

Permitting reform: what S. 5653 would do

The Senate bill was introduced on 30 September by Senators Shelley Moore Capito, Mike Lee, Sheldon Whitehouse and Martin Heinrich, according to the IHMM summary, which also notes that the House passed a narrower bill, the SPEED Act (H.R. 4776), on 18 December 2025. The bill text lists energy storage projects, pumped storage hydropower and long-duration battery storage among its project categories. It also includes a provision covering batteries built on previously disturbed or developed land and a programme for voluntary streamlined local permitting of distributed energy systems, including battery systems.

Solar Power World reports that the bill names solar, storage and onshore and offshore wind, and also covers natural gas, oil and coal. More than 300 solar and storage companies have signed a letter backing it, and their press release argues that voters in the midterm elections made lower energy costs a top concern.

The National Association of Counties says the sponsors released a substitute text on 7 November, ahead of a cloture vote scheduled for 9 November. We did not find a confirmed result. The bill is not law, and the Senate and House versions would have to be reconciled.

Who gains and who loses

The data does not yet show winners, since the DOE rules are unwritten. A likely reading is that the effects would fall unevenly.

  • Possible gainers: manufacturers and integrators with US or non-covered supply, and developers whose projects sit on previously disturbed land if the permitting provisions survive. Rystad’s finding of lower reliance on Chinese transformers and inverters suggests those categories face less disruption.
  • Possible losers: developers with contracts for imported battery systems, data centre operators buying backup batteries, and utilities counting on delivery dates. BloombergNEF expects delays and cancellations.
  • Uncertain: integrators with large backlogs.

The political backdrop

Energy-Storage.news reports that Democrats took both the House and the Senate in the midterm elections. Derrick Flakoll of BloombergNEF said he expects the results to be a net positive for storage over the next two years, as newly unified Democratic state governments pass stronger renewable and storage standards. He also flagged open questions on interconnection reform and data centre development.

That is one analyst’s view. The order is an executive action, so a change in congressional control does not by itself alter it.

A comparison: the same barriers in Europe

Permitting and grid access are not only US issues. The European Commission’s Joint Research Centre reports that EU storage power capacity stands at 76 GW against 172 GW needed by 2030 under the Commission’s impact assessment. It identifies grid connection delays, regulatory uncertainty and limited long-term revenue visibility as the most persistent barriers.

Risks and open questions

  • The DOE has not said which suppliers, components or software would be covered, or how existing contracts and installed systems would be treated.
  • Permitting changes would speed approvals but would not supply batteries; the two constraints could bind at different times.
  • Fluence’s backlog conversion depends on its Houston ramp-up, which has already slipped.
  • Rystad and BloombergNEF are analysts’ assessments, not measured outcomes, and the first rules may be narrower than the text of the order suggests.

What to watch

  • The result of the Senate cloture vote on S. 5653 and any House response.
  • The DOE’s implementing rules, due by 24 December 2026, and whether they exempt existing contracts.
  • Fluence’s fiscal 2026 results and its promised fiscal 2027 plan, plus the choice of permanent CEO and CFO.
  • Whether the Ford Energy and DESRI partnership and similar domestic deals publish volumes and delivery dates.
  • State-level storage standards from newly unified governments, as BloombergNEF anticipates.