EU clears €2.04bn Belgian aid for first Princess Elisabeth wind farm

The European Commission approved a €2.04 billion Belgian State aid scheme on 10 November 2026 to support the first offshore wind farm in the Princess Elisabeth Zone in the Belgian North Sea, reNEWS reports.

The scheme runs for 20 years and was cleared under the Commission’s Clean Industrial Deal State Aid Framework (CISAF), adopted in June 2025. MLex reports that support will be awarded through competitive bidding and two-way contracts for difference, with tender criteria requiring supply-chain diversification away from imports from outside Europe.

At a glance

Item Detail
What State aid scheme, 20-year two-way CfD
Who Belgium, approved by the European Commission
Where Princess Elisabeth Zone, Belgian North Sea
Size €2.04 billion; up to 735 MW (Brussels Times)
Status Aid approved 10 November 2026; tender not yet relaunched

Context

The new decision replaces a €682 million scheme the Commission approved in September 2024 under its crisis framework. According to reNEWS, funding under that scheme was not granted before its legal deadline of 31 December 2025. Our calculation: €2,040m ÷ €682m ≈ 3.0, so the ceiling is about three times the earlier figure.

Belgium halted the first tender in July 2025. Riviera Maritime Media reports the causes included a tight timeline set by EU State aid rules and delays to the offshore energy island that the zone’s farms will connect to.

What is new

In July 2026 the Belgian government approved a revised framework, according to Enerdata. It extends the maximum construction period from four to five years, removes the price cap and sets a single two-sided CfD.

The Brussels Times reports that support will be calculated on the farm’s theoretical capacity, not the electricity actually delivered to the grid. Capacity is cited as up to 735 MW there, while earlier Belgian and Commission documents describe roughly 700 MW.

What to watch

Belgium has said it will relaunch the PEZ 1 tender once remaining steps, including a Council of State review, are complete; no date has been published in the sources reviewed. Bidder response to the revised CfD and supply-chain rules will be the first test of the redesign.