Norway pauses new data centre grid reservations until 2027

Norway’s transmission system operator Statnett has stopped accepting new grid capacity reservations from data centres, with the pause expected to be lifted no later than 1 August 2027, DatacenterDynamics reports. The step came on Monday 9 November 2026, alongside a government plan for a data centre licensing scheme.

At a glance

Item Detail
What Pause on new data centre capacity reservations and some technical approvals
Who Statnett (grid operator) and the Norwegian government
Where Norway, national grid

What is paused, and what is not

Statnett is also holding back new technical-approval applications and pending applications for facilities that connect directly to its 420 kV network, The Energy Mag reports. It cited fast changes in consumption and the way facilities respond to grid disturbances. Projects already connected or already approved are unaffected, and Statnett has pledged to protect existing queue positions.

The government says it wants to steer growth. Digitalization Minister Torgeir Micaelsen said: “We want data centers in Norway, but we can’t have all types of data centers.” A licensing scheme is expected to favour defence, health, emergency services and other critical infrastructure.

The queue against peak demand

Statnett’s figures, as of 9 November 2026: around 800MW of data centres are connected, 4.2GW is reserved and 9.1GW is in the capacity queue. A further 18GW has been requested. Norway’s peak consumption is just above 25 GW, according to Briefs.

Our calculation: 0.8 + 4.2 + 9.1 + 18 = 32.1 GW across the four stages, or about 1.3 times a 25 GW peak (32.1 / 25 = 1.28). This assumes the stages are separate and do not overlap, and the requests are preliminary.

Norway data centre grid pipeline by stage, as of 9 November 2026. Data centre capacity: Connected 0.8, Reserved 4.2, In capacity queue 9.1, Requested 18 (GW)
Norway data centre grid pipeline by stage, as of 9 November 2026
Source: Statnett figures as reported by DatacenterDynamics, 9 November 2026

The industry body Norsk Datasenterindustri says the decision and licensing plan create uncertainty for investments worth several billion kroner a month, according to Briefs. The government also plans higher grid-cost contributions from large new users, The Tech Capital reports.

What to watch

Look for the licensing criteria and the grid-cost rules, which will decide who gets capacity when reservations reopen. Statnett’s stronger technical requirements for how large loads behave during grid disturbances are the other item to follow.