Week in renewables: grid links and permitting take centre stage

SSE wins a cable consent for Berwick Bank C

SSE Renewables has secured a marine licence from the UK’s Marine Management Organisation for the export cables of Berwick Bank C in English waters, Offshore Wind reports. SSE says the approved infrastructure will provide up to 1.8 GW of transmission capacity, using up to four HVDC cables landing at Cambois near Blyth in Northumberland, according to Infrastructure Now.

The wider 4.1 GW project received Scottish government consent in July 2025. The 1.4 GW Berwick Bank B phase holds a 20-year contract for difference from the January 2026 UK auction, and SSE expects a final investment decision in 2027.

Solar and storage firms press the US Senate on permitting

More than 300 solar and storage companies signed a 9 November letter urging Congress to pass the Bipartisan American Affordability and Jobs Act (S. 5653), the Solar Energy Industries Association (SEIA) says. The bill was introduced on 30 September 2026 by Senator Shelley Moore Capito, a Republican, with Senators Lee, Whitehouse and Heinrich.

SEIA’s own analysis says the bill could add 167 GW of solar capacity between 2028 and 2035. Solar Builder reports that Congress must act before the 119th Congress adjourns or the bill restarts in 2027.

India approves a 1,150-kV transmission corridor

India’s national transmission panel has approved what would be the country’s highest-voltage network, Reuters reported via Business Standard on 11 November 2026. The cost is estimated at nearly 688 billion rupees ($7.34 billion), with about six years to build.

The first phase links Chhattisgarh, Odisha and West Bengal and connects to a 6,000 MW system carrying power from Rajasthan’s Bhadla solar region. Existing lines run at 765 kV.

Our calculation: $7.34 billion over about 6 years is roughly $1.22 billion per year of construction spending, assuming even phasing.

Calibrant closes $145 million facility, including a data centre battery

Calibrant Energy announced on 10 November a $145 million debt facility led by Investec, with Citi, Liberty Bank and Siemens Financial Services also taking part, Energy-Storage.News reports. The portfolio includes a 120 MWh battery serving a hyperscale data centre customer in the PJM market.

The company, backed by Macquarie Asset Management, says its storage portfolio exceeds 5.9 GWh across operating, under-construction and exclusively contracted projects. The press release does not give detailed debt terms.

Colorado nonprofit starts a plug-in solar programme

Solar Access Colorado has launched ahead of a new state law on plug-in and balcony solar, Solar Power World reports. The group describes itself as the state’s first organisation dedicated to such systems and says it targets households long left out of the residential solar market.

Sungrow unveils a third-generation C&I storage system

pv magazine reports that Sungrow has launched its third-generation commercial and industrial storage system on 12 November 2026. The company says it is built around a modular expansion-dock architecture for several use cases, with a power conversion system based entirely on silicon carbide.

The week at a glance

Story Topic Region Size or value Source
Berwick Bank C cable licence Offshore wind UK Up to 1.8 GW transmission; 4.1 GW project Offshore Wind
BAAJA letter (S. 5653) Permitting policy US federal 300+ companies; SEIA estimate of 167 GW solar SEIA
1,150-kV corridor Transmission India $7.34 billion; 6 years Reuters
Calibrant debt facility Storage finance US (PJM and other markets) $145 million; 120 MWh battery Energy-Storage.News
Solar Access Colorado Plug-in solar Colorado, US Programme launch; no capacity stated Solar Power World
Sungrow C&I system Storage product Global Third generation; no capacity stated pv magazine

Next week

The sources reviewed for this round-up list no dated events for the coming week. The nearest fixed date is 30 November 2026, the deadline Reuters says India’s power ministry set for renewable energy implementation agencies to consider power purchase agreements for stranded projects, according to MarketScreener’s copy of the report.