Germany’s onshore turbine makers have the orders and the factory capacity for a construction boom, but road transport rules could hold the machines back, executives told Reuters on 6 November 2026. The warning arrives as permitting and auction data point the same way: the pipeline is filling faster than turbines are reaching sites.
This analysis sets out what the manufacturers said, what the official data shows, who benefits and who bears the cost, and where the evidence stops.
What the manufacturers told Reuters
Enercon, the privately owned German maker, expects annual installations in Germany to reach 10-11 GW in 2028, roughly double last year’s level. Berlin has proposed auctioning 15 GW of onshore capacity in both 2027 and 2028, up from around 10 GW this year. That auction volume is a proposal, not adopted policy.
Enercon, Nordex and Vestas supplied 97% of Germany’s newly installed onshore wind capacity in the first nine months of 2026. Nordex says its planned German installations for 2027 are already covered by orders, with a “good portion” of 2028 also booked.
The constraint sits outside the factories. Nordex chief executive Jose Luis Blanco said the company is installing fewer turbines in Germany than planned because some sites were not ready and transport permits were arriving too slowly. Enercon executive Benjamin Seifert called transport permits “a real bottleneck in Germany”, adding that operators must have trucks lined up and apply early. A Swedish-language summary of the Reuters report by Börsvärlden adds that a shortage of construction crews, specialised tower suppliers and delayed grid connections are further pinch points.
The problem is not new. In 2023 Reuters reported a backlog of more than 15,000 transport-permit applications, and an Enercon spokesperson estimated the delays could add 115 million euros to the company’s costs by the end of that year. The 2023 report also noted that permits are needed to move heavy loads over bridges and highways, and that some structures and road signs have to be dismantled for the trip.
The numbers behind the bottleneck
The Fachagentur Wind und Solar, an industry agency working for the BWE wind association, counted 3,310 permitted turbines with 20,765 MW in 2025. In the same year 958 turbines with 5,232 MW were commissioned. In the first half of 2026, newly approved capacity rose 14 percent to a new record of 9.1 GW, while 423 turbines with 2,363 MW were commissioned.
| Indicator | Value | Period | Source |
|---|---|---|---|
| Installed onshore capacity (GW) | 68.1 | End of 2025 | Bundesnetzagentur |
| 2030 onshore target (GW) | 115 | Legal target | Bundesnetzagentur |
| Average annual additions needed (GW) | 9.4 | To 2030 | Bundesnetzagentur |
| Capacity permitted (GW) | 20.8 | 2025 | Fachagentur Wind und Solar |
| Capacity commissioned (GW) | 5.2 | 2025 | Fachagentur Wind und Solar |
| Capacity permitted (GW) | 9.1 | H1 2026 | VDMA / Fachagentur |
| Capacity commissioned (GW) | 2.4 | H1 2026 | VDMA / Fachagentur |
The Bundesnetzagentur put installed onshore capacity at 68.1 GW at the end of 2025, against a 2030 target of 115 GW. It calculates that Germany needs an average of 9.4 GW of new capacity each year to get there. Net growth in 2025 was 4.6 GW, because turbines were also retired, mostly to be repowered.

Source: Fachagentur Wind und Solar (2025); VDMA/Fachagentur half-year report (H1 2026); figures rounded
The chart compares permitted and commissioned capacity. Permits in 2025 ran at about four times commissioned capacity (20.8 GW against 5.2 GW). The first half of 2026 shows a ratio near 3.8 (9.1 GW against 2.4 GW), rounded figures in both cases.
Permitting got faster, so the queue moved downstream
Approval times improved. The Fachagentur reported an average completion time of 17 months in 2025, 28 percent less than in 2024. A permit is only one step, though: for projects that won auction contracts and have been built, the half-year status report counts an average of 20.6 months from award to commissioning.
The same report says processes for oversized and heavy-goods transport are increasingly becoming a bottleneck for turbine construction. WindEurope’s chief executive Giles Dickson made a similar point about Germany in 2024, saying the country needs to ensure transport permits are granted faster and less bureaucratically.
The Fachagentur’s early-2026 forecast was that gross expansion in 2026 is likely to reach 8 to 8.5 GW, if implementation pace held and failure rates stayed low. Our calculation: with 2.36 GW commissioned in the first half, an 8 GW year needs 8.0 – 2.36 = 5.64 GW in the second half, about 2.4 times the first-half pace (5.64 / 2.36). In 2025, the first half delivered 2.2 GW of a 5.2 GW year, so a back-loaded year is normal, but the 2026 gap is wide. The agency’s forecast predates the manufacturers’ warning, and no later official estimate was found.
Auction prices keep falling
Competition among project developers has pushed award prices down for seven consecutive rounds. The Bundesnetzagentur says that since August 2024 the average award price has fallen by more than 2 ct/kWh. The 1 August 2026 round awarded 237 bids with a total volume of 2,523 MW from 461 bids totalling 5,250 MW, at a volume-weighted average of 4.79 ct/kWh, down from 5.06 ct/kWh.
The agency’s price ceiling for 2026 rounds is 7.25 ct/kWh, so winning bids now sit well below it. The reNEWS report on the earlier round says its average of 5.54 ct/kWh was the lowest since the February 2018 auction.

Source: Bundesnetzagentur press releases; reNEWS (March 2026 result)
Our calculation: from 6.06 ct/kWh to 4.79 ct/kWh across the four results shown is a fall of (6.06 – 4.79) / 6.06 = 21%. These are pay-as-bid prices under the Renewable Energy Sources Act, and the award value is the basis for calculating the market premium.
Oversubscription is easing even as prices fall. Bids offered were 7,858 MW in the March 2026 result, 6,409 MW in the 1 May round and 5,250 MW in August.
Who gains and who loses
Turbine makers with full order books gain most clearly, provided they can deliver. Nordex, for example, reported 10,200 MW of total orders in 2025, an all-time high for the company. Consumers and the federal budget benefit from lower awarded prices, since lower values mean lower market premium payments in later years.
Developers carry the timing risk. A project with an awarded contract and a permit still needs trucks, route approvals and a ready site, and delay raises financing and storage costs. The sources reviewed do not say how contracts split those costs between developer and manufacturer, so that is unconfirmed.
Transport firms and road authorities sit at the centre. They are the party most able to ease the constraint, yet the 2023 Reuters report noted the lack of a single national procedure, with each federal state setting different requirements and documentation. Whether that has changed since is not covered in the sources used here.
Competing readings
The industry’s own framing is optimistic about volume. The BWE-commissioned analysis counts record approvals and tenders oversubscribed by a factor of two and a half in the first half of 2026. Manufacturers add a caveat: capacity to build exists, but delivery depends on infrastructure and procedures outside their control.
The data shows a growing gap between permitted and built capacity, falling award prices and a manufacturer base that is almost fully booked for 2027. A likely reading is that the binding constraint has moved from permits to logistics and site readiness, and that falling prices make delays costlier for developers working on thin margins. Another reading, which the numbers cannot rule out, is that some of the permitted capacity will not be built, since the 2025 rise in permits has not yet fed through to commissioning. Both are interpretation, not measured outcomes.
Risks and open questions
- Delivery against targets. Germany’s 115 GW goal for 2030 requires an average of 9.4 GW a year; 2025 delivered 5.2 GW gross, and the Fachagentur forecast 8 to 8.5 GW for 2026.
- Bid thinning. Falling bid volumes could signal either developer caution at low prices or a shrinking supply of ready projects. The Bundesnetzagentur has not attributed it.
- Repowering and retirements. The half-year report notes that 12.2 GW of capacity is no longer supported since the start of 2026 under the subsidy scheme, which raises replacement pressure on the same transport chain.
- Auction volume. The proposed 15 GW a year for 2027 and 2028 would add pressure to every step, and is not yet law.
What to watch
Watch the next Fachagentur Wind und Solar data for full-year 2026 commissioning against its 8 to 8.5 GW forecast. The Bundesnetzagentur’s next onshore auction results will show whether award prices continue below 4.79 ct/kWh and whether bid volumes keep thinning. Also look for any federal or state reform of heavy-load transport permitting, and for Nordex and Enercon updates on how many turbines slipped from their 2026 plans. Parliament’s decision on the 15 GW auction volumes for 2027 and 2028 will set the scale of the load the road network must carry.
Sources
- Global Banking & Finance (Reuters report): Germany’s onshore wind boom faces logistical hurdles as turbine orders surge
- Bundesnetzagentur: Growth in renewable energy in 2025
- Bundesnetzagentur: High level of competition in May onshore wind and innovation auctions
- Bundesnetzagentur: Onshore wind auction that ended on 1 August 2026 greatly oversubscribed
- Bundesnetzagentur: Determination of price ceilings for 2026 auctions for onshore wind and roof-mounted solar
- Fachagentur Wind und Solar: Status of Onshore Wind Energy Development in Germany, Year 2025
- VDMA: Status of Onshore Wind Energy Development in Germany, First Half of 2026
- Clean Energy Wire: Germany continues record streak for onshore wind power approvals in first half of 2026
- Clean Energy Wire: Germany approves record capacity for new onshore wind turbines in 2025
- reNEWS: Germany awards 3.4GW in onshore wind tender
- WindEurope: German onshore wind sees record auction volumes, permitting improvements and new port investments
- Renewable Energy Industry: Nordex Group once again market leader in onshore wind power in Germany in 2025
- MarketScreener (Reuters report): Germany’s wind power expansion stalls on the roads
- GreentechLead: Germany’s wind power expansion hampered by permit backlog
- Börsvärlden: Transportproblem hotar Tysklands utbyggnad av vindkraft
- Baltic Wind: German onshore wind auction oversubscribed again
- Mercom India: Germany awards 2.52 GW in oversubscribed onshore wind auction
Header image: illustration, AI-generated.