Ofgem probes why UK grid queue reform pushed connection dates back

Ofgem has opened an urgent inquiry into why most projects in Great Britain’s reformed grid connections queue have been given later connection dates than they held before the reform. The regulator announced it on 19 November 2026, saying the clean-up removed speculative capacity but that outcomes for many “protected” and Phase 1 projects are not good enough.

What Ofgem said on 19 November

In its announcement, Ofgem says connections reform has cleared significant speculative capacity and created a more credible pipeline. It adds that the majority of projects in the reformed queue are seeing delays rather than advancements compared with their pre-reform position.

The inquiry will examine why offers for protected and Phase 1 projects slipped, including how the picture differs across network companies. Ofgem says it will also draw lessons for future connection windows, explore stronger automatic compensation where networks cause delays, and take enforcement action if it finds a material breach of licence obligations by NESO (the National Energy System Operator) or a network company.

Energy Live News reports that the first detailed findings are due in Ofgem’s Infrastructure Progress Report in February. The Financial Times, as summarised by Traders Union, quotes Ofgem’s director-general for infrastructure, Akshay Kaul, saying the dates offered to too many projects are not good enough. The same summary says NESO supports the inquiry and that nearly 200 projects have received earlier dates.

The numbers behind the queue

Before reform, Great Britain’s connections queue stood at 722 GW, roughly four times the capacity required, according to Knight Frank’s summary of NESO’s results. On 8 December 2025, NESO confirmed 283 GW of generation and storage and 99 GW of transmission-connected demand as successful. These were split into Phase 1 (connection by 2030) and Phase 2 (by 2035).

Great Britain connections queue: before and after reform. Capacity (GW): Pre-reform queue 722, Gate 2 generation and storage 283, Gate 2 transmission demand 99 (GW)
Great Britain connections queue: before and after reform
Source: NESO results of 8 December 2025 as summarised by Knight Frank

Our calculation: (722 GW − 283 GW) ÷ 722 GW = 439 ÷ 722 ≈ 61% of the pre-reform queue’s generation and storage capacity did not make the new pipeline. The comparison is approximate, because the 722 GW figure is Knight Frank’s description of the old queue and 283 GW covers generation and storage only.

The reform trimmed technologies unevenly. Knight Frank says solar and onshore wind kept some headroom while battery projects were significantly cut and remain above target capacity ranges. Modo Energy’s 2026 roadmap estimated the battery pipeline at around three times the capacity implied by the Clean Power 2030 targets.

A timetable that kept moving

The slippage is visible in the offer schedule itself. NESO’s original timeline, as set out by consultancy TNEI, called for Phase 1 offers by the end of the second quarter of 2026. The deadline has since been extended twice.

Date Event Detail
8 December 2025 NESO publishes queue results 283 GW generation and storage, 99 GW demand in the new pipeline
February 2026 Ofgem refuses relief request Declines to excuse NESO and transmission owners from obligations on delayed protected-project dates
10 June 2026 Offers milestone 713 projects, about 37 GW, hold updated agreements, says NESO
October 2026 Second extension Phase 1 offers due by 31 October; distribution offers by 30 November
19 November 2026 Inquiry opened Ofgem examines delays to protected and Phase 1 projects
31 January 2027 Phase 2 deadline Offers for projects connecting 2031 to 2035

The February step is documented in Solar Power Portal’s report, whose headline refers to delays affecting 62% of Gate 2 project connections. Ofgem said at the time it was frustrated and disappointed that existing dates could not be met for all projects qualifying for protection. Per the same report, the delays were largely network-related, and 75 projects were delayed solely by developer issues.

The June milestone comes from Renews, which quotes NESO’s chief operating officer, Kayte O’Neill, calling it a sign that reform is delivering results. In October, Renews reported that NESO had issued 75% of Phase 1 offers and attributed the extra month mainly to delays by National Grid Electricity Transmission in providing construction offers, citing “complexity and engineering considerations”. The dates come from Ofgem’s letter agreeing the revised timetable.

Who gains and who loses

The data shows a split outcome. NESO says nearly 200 projects got earlier dates, while Ofgem says the majority moved the other way. Both statements can hold at once if a minority of well-placed projects advanced while a larger group slipped.

Group Position Basis
Projects with later dates Lose revenue timing and financing certainty Ofgem: most of the reformed queue saw delays
Projects with earlier dates Gain NESO: nearly 200 projects
Batteries Squeezed by a large pipeline Knight Frank, Modo Energy
Network owners Growing regulated earnings SSE half-year results
Bill payers Exposed to constraint and network costs Ofgem RIIO-3 context; unquantified for this inquiry

Developers bear the commercial risk. Energy Live News notes that investment decisions are built around connection dates. In the FT’s reporting, a developer said uncertainty during reform has largely stalled decision-making, with one project pushed back two years. That is one developer’s account and is not a measure of the wider queue.

Network owners are on the other side of the ledger. SSE says it invested a record £2.6bn in the first half of its financial year, up 63%, with around 70% in electricity networks, and expects more than £5bn for the full year. Per SSE, networks contributed about two-thirds of adjusted operating profit, which Renews reports rose to £1.1bn from £655m. SSE also says all 11 major SSEN Transmission projects are now under construction in full or in part, as Windtech International relays.

Regulated returns grow with spending, which is why the delivery record matters to the regulator. A reading consistent with the evidence is that the physical works behind the dates, not the queue software, are the constraint. That is an interpretation; the inquiry exists to establish the causes.

Competing views

Ofgem’s position is that reform was necessary and its results are unacceptable. It says it will “share” developers’ frustration, in the words reported by the Financial Times, and warns that complexity cannot be allowed to obscure poor performance. It has also asked whether any dates can be brought forward.

NESO’s position is that reform removed speculative capacity, issued offers to more than 700 projects by June, and improved dates for nearly 200. It has pointed to dependencies on transmission owners for construction offers.

Developers describe a different cost. The FT reporting says reassessment since July 2025 paused substation building and stalled supply chains. Developers want firm dates and compensation, and Ofgem says it sees no reason connection agreements cannot contain compensation provisions now.

Demand is arriving in the same queue

Generation is not the only claimant. According to NESO figures cited by the Scottish Greens, around 30 hyperscale data centre proposals in Scotland would require 9.7 GW of demand. The party’s analysis, published on its website, is a counterfactual: it estimates typical Scottish household electricity bills would be about £317 a year higher had all been operating from October 2024.

A technology-sector view put to MSPs, reported by Brit Brief, was that claims data centres will lift household bills are misinformation. The disagreement shows how demand allocation in the queue is turning into a bill-impact argument, a topic Ofgem’s inquiry does not directly address.

Risks and open questions

  • Cause. Ofgem has not yet said whether delays stem from NESO’s process, transmission owners’ engineering, developer readiness, or all three. It says the picture may differ across network companies.
  • Compensation design. Automatic compensation is under exploration only. Who pays, and whether costs pass to consumers, is not settled.
  • Investor confidence. If a confirmed Gate 2 date can move, its value as evidence of readiness weakens.
  • Remaining offers. Phase 2 offers are due by 31 January 2027, and a repeat of Phase 1 slippage would hit projects aiming at 2031 to 2035.
  • Enforcement. A licence breach finding against NESO or a network owner would be a new step for the reformed regime; Ofgem has only said it will not hesitate if one is found.

What to watch

Ofgem’s deadline for completing Phase 1 distribution offers is 30 November 2026. Confirmation from NESO that all Phase 1 offers are issued, as the October letter requires, will show whether the schedule has finally held.

Next come the 31 January 2027 Phase 2 deadline and the February Infrastructure Progress Report, the first detailed findings Ofgem has promised. Watch for any licence breach finding, for compensation terms appearing in connection agreements, and for SSEN Distribution’s 2028 to 2033 business plan, which SSE says it will submit shortly.