Ren-Gas takes FID on €300m e-methane plant in Tampere, Finland

Finland’s Nordic Ren-Gas took a final investment decision (FID) on 20 November 2026 on a green hydrogen-based e-methane plant in Tampere, a project of more than €300m, with construction starting immediately and production targeted for 2029.

At a glance

Item Detail
Developer Nordic Ren-Gas (Finland)
Site Tarastenjärvi, Tampere, beside the Tammervoima waste-to-energy plant
Electrolyser 50MW Sunfire alkaline unit
Output About 190GWh of e-methane per year at full capacity
Status (20 November 2026) FID taken; construction beginning; start-up targeted for 2029

What the plant will do

Gasworld reports that the plant will combine hydrogen from the electrolyser with 40,000 tonnes of biogenic carbon dioxide a year captured from a local waste-to-energy plant. The e-methane will enter cross-border gas networks and be claimed for heavy-duty truck refuelling in Germany by subsidiaries of Avanca Energy, under a €1bn offtake deal signed in July 2026.

Daily Northern, citing Yle, says the investment exceeds €300m. It lists the European Investment Bank, Societe Generale, Standard Chartered, Nordea and Finnvera as debt providers, with the EIB’s share a €60m loan backed by InvestEU. The process will also send about 200GWh of waste heat a year to Tampere’s district heating network.

Why it matters

Hydrogen Insight headlines the project as the world’s largest green hydrogen-based synthetic methane plant to reach FID; the company makes a similar claim, and we have not verified it independently. Ren-Gas’s other Finnish plans include a 50MW project in Lahti, which gasworld says won €45m in European Hydrogen Bank production subsidies.

Gasworld reads the FID as a sign that the binding hydrogen mandates in the EU’s RED III directive are starting to produce investment decisions. It adds that proposals to weaken those mandates have worried the sector, because developers rely on demand certainty.

Our calculation: €300m ÷ 190GWh a year ≈ €1.58m of capital cost per GWh of annual output. This is a floor, because reported costs exceed €300m, and it excludes financing and operating costs.

What to watch

Watch whether construction milestones and the 2029 start-up date hold, and whether the EU mandates behind the offtake demand stay unchanged as the weakening proposals move through the legislative process.