Öresundskraft takes FID on SEK 2.4bn Helsingborg carbon capture

Swedish municipal utility Öresundskraft has taken a final investment decision (FID) on a carbon capture and storage unit at its Filbornaverket waste-to-energy plant in Helsingborg, designed to capture about 200,000 tonnes of CO2 a year. Open Access Government reports that approval came on 30 September 2026; Carbon Herald covered the decision on 16 November 2026.

At a glance

Item Detail
Project INNOZHERO CCS at Filbornaverket, Helsingborg, Sweden
Developer Öresundskraft (municipal utility)
Capture capacity About 200,000 t CO2 a year, fossil and biogenic
Cost SEK 2.4 billion
Status FID taken 30 September 2026; construction to start late 2026; operation planned 2029

What the decision covers

The company says the plant will be the first waste incineration facility in the EU to reach FID for the full chain of capture, transport and permanent storage, according to Recyclingnet. We could not check that claim against a second independent source.

Carbon Capture Journal reports that the CO2 will be liquefied on site and trucked to the Port of Halland in Halmstad. Northern Lights, the Norwegian transport and storage venture, will take it for storage under the North Sea. Byggvärlden lists the biogenic share of the CO2 at 40 to 45 per cent, and support from the EU Innovation Fund and the Swedish Energy Agency at about SEK 830 million.

Cost and offtake

Sources disagree on whether the SEK 2.4 billion figure includes grants: Energi.se says it excludes them, while Recyclingnet says it includes them. Our calculation: SEK 2,400,000,000 ÷ 200,000 t = SEK 12,000 of capital cost per tonne of annual capture capacity.

Öresundskraft has also signed a ten-year carbon removals purchase agreement with the metal powder maker Höganäs, Bioenergy International reports. The company expects the project to avoid almost 1.9 million tonnes of emissions in its first ten years, according to Open Access Government; that is a company projection, not measured data.

What to watch

Construction is due to start towards the end of 2026, so site works and the first equipment deliveries should show whether the 2029 start-up date holds. The share of CO2 sold as carbon removals will depend on further offtake contracts beyond Höganäs.